Validation for OPS Sign-Up Management

Validation messages, causes, and fixes for OPS Sign-Up Management.

Table 1. OPS Sign-Up Management Validation
Message Additional Detail Fix
Cannot find sign-up period for Id:[99999] in the schedule. The import process failed and the sign-up period was not created. Contact your Trapeze representative.
Cannot find the associated block for the pullout run [xxxxx], piece [99999] [SourceId:[99999], ExcComboId:[99999], SourceBlockId:[99999], BlockVersionId:[99999] The block referenced by the run cannot be found. Examine your data to see why the block is missing (Inadvertently deleted, not included in original schedule data).
Cannot find the associated block for the pullin run [xxxxx], piece [99999] [SourceId:[99999], ExcComboId:[99999], SourceBlockId:[99999], BlockVersionId:[99999] The block referenced by the run cannot be found. Examine your data to see why the block is missing (Inadvertently deleted, not included in original schedule data).
Work [xxxxx] has a from time hh:mm:ss from [xxxxx] that is less than the sign-on time hh:mm:ss. Correct the schedule and reimport. The work's start time is earlier than the sign-on time. Correct the schedule and reimport.
Work [xxxxx] has a to time [hh:mm:ss] from [xxxxx] that is greater than the sign-off time [hh:mm:ss]. Correct the schedule and reimport. The sign-off time is earlier than the to time of the work. Correct the schedule and reimport.
Work [xxxxx] has a sign-on time hh:mm:ss that is greater than the sign-off time hh:mm:ss. Correct the schedule and reimport. The sign-on time is later than the sign-off time. Correct the schedule and reimport.
Cannot find the associated block for work [xxxxx]. Correct the schedule and reimport. The block referenced by the run cannot be found. Examine your data to see why the block is missing (Inadvertently deleted, not included in original schedule data).
Work [xxxxx] has a mismatch in start block [xxxxx] and end block [xxxxx]. The work does not start and end on the same block. The run is not imported. Correct the schedule and reimport.

No changes were made to sign-up period [xxxxx] because there were activated days in the adjustment period of [mm-dd-yyyy] to [mm-dd-yyyy].

On the Activate Day screen, use the Undo Day Activation feature to undo activation for the activated days within the sign-up period.

No changes were made to sign-up period [xxxxx] because no schedule versions could be found for it.

Records for this sign-up period were not correctly entered in the database. Contact your Trapeze representative.