Validation for OPS Sign-Up Management
Validation messages, causes, and fixes for OPS Sign-Up Management.
| Message | Additional Detail | Fix |
|---|---|---|
| Cannot find sign-up period for Id:[99999] in the schedule. | The import process failed and the sign-up period was not created. | Contact your Trapeze representative. |
| Cannot find the associated block for the pullout run [xxxxx], piece [99999] [SourceId:[99999], ExcComboId:[99999], SourceBlockId:[99999], BlockVersionId:[99999] | The block referenced by the run cannot be found. | Examine your data to see why the block is missing (Inadvertently deleted, not included in original schedule data). |
| Cannot find the associated block for the pullin run [xxxxx], piece [99999] [SourceId:[99999], ExcComboId:[99999], SourceBlockId:[99999], BlockVersionId:[99999] | The block referenced by the run cannot be found. | Examine your data to see why the block is missing (Inadvertently deleted, not included in original schedule data). |
| Work [xxxxx] has a from time hh:mm:ss from [xxxxx] that is less than the sign-on time hh:mm:ss. Correct the schedule and reimport. | The work's start time is earlier than the sign-on time. | Correct the schedule and reimport. |
| Work [xxxxx] has a to time [hh:mm:ss] from [xxxxx] that is greater than the sign-off time [hh:mm:ss]. Correct the schedule and reimport. | The sign-off time is earlier than the to time of the work. | Correct the schedule and reimport. |
| Work [xxxxx] has a sign-on time hh:mm:ss that is greater than the sign-off time hh:mm:ss. Correct the schedule and reimport. | The sign-on time is later than the sign-off time. | Correct the schedule and reimport. |
| Cannot find the associated block for work [xxxxx]. Correct the schedule and reimport. | The block referenced by the run cannot be found. | Examine your data to see why the block is missing (Inadvertently deleted, not included in original schedule data). |
| Work [xxxxx] has a mismatch in start block [xxxxx] and end block [xxxxx]. | The work does not start and end on the same block. The run is not imported. | Correct the schedule and reimport. |
|
No changes were made to sign-up period [xxxxx] because there were activated days in the adjustment period of [mm-dd-yyyy] to [mm-dd-yyyy]. |
— | On the Activate Day screen, use the Undo Day Activation feature to undo activation for the activated days within the sign-up period. |
|
No changes were made to sign-up period [xxxxx] because no schedule versions could be found for it. |
Records for this sign-up period were not correctly entered in the database. | Contact your Trapeze representative. |