Manually Loading Schedules

Load schedules into the system so that you can work with them.

Before you begin

Schedule Administrator must be open.

About this task

After you set up the automatic loading of schedules, the Schedule Server loads and unloads schedules for you on a daily basis. If you want to view a past schedule that the Schedule Server has unloaded or work with a future schedule that has not yet been loaded, you must manually load that schedule.

Procedure

  1. Select the schedule to be loaded.
    If you want to load a future schedule that is not currently in the list, you will first need to add it.
    Up to ten schedules can be selected at once by holding the CTRL key and clicking the schedules.
  2. Click Schedule > Load.

Results

Any selected rows are marked with an L in the Status column. This indicates that the schedules have been loaded.