Overriding Costs of Runs
The Override Costing feature allows you to manually change the cost of a run.
The values shown in the Run pane of the Run Costing dialog are based on what you have defined on the Parameters tabs.
-
On the Run Cost dialog, click Override
Costing.
The Save and Cancel buttons appear and you can edit the fields in the dialog.
- Overwrite the values of the fields you want to change.
-
Click Save.
The run is marked with an “O” in the St (Status) column in the Runs screen.Note:
Runs which are frozen (F), forced (M), and have their costs overridden (O) are not affected when you recut the runs using the Automatic Runcutting feature unless you choose the Cut All Blocks by Scratch option.