Removing runs refers to taking runs from a roster and creating a new roster with
them.
Make sure that the previously defined rosters have been loaded
on the Rostering screen and the Edit tab is open.
Depending on the combinations of the runs you select in the
Roster grid, the check boxes in the Remove
frame appear activated or shaded. The following steps use examples of rosters that you may
want to create:
-
Select a 7-day roster (no Off days created yet) in the Roster
grid. to activate .
The check boxes of all days of the week are selected in the
Remove frame. (If you selected a 5-day roster, the check boxes
of the weekdays are activated while the check boxes for Saturday
and Sunday appear shaded.)
-
In a 7-day roster, select the Mo (Monday) and
Tu (Tuesday) check boxes and click Remove.
The two run numbers are removed from the selected roster and become a 2-day On
roster. The original 7-day On roster becomes a 5-day On roster.
-
Select the Split runs check box.
The system takes the two days and puts them into two separate one-day rosters,
thereby creating in this example, a Monday roster and a separate Tuesday roster.
If you
attempt to remove rosters that have been assigned Off Days, you are notified that they
cannot be changed.
If you have selected several rosters that are frozen, a similar
message also appears.
-
To proceed with the removal of the selected rosters, click
Yes.