Copying Provider Contract Validities

If a new provider contract validity will be similar to an existing contract validity, copy the original and modify the copy as needed.

Before you begin

The Trapeze4 Workstation must be open to Provider Contracts ancillary data.

About this task

For example, if this is the second year of a contract, an easy way to make minimal rate adjustments is to copy last year's validity, apply the correct dates, and edit the validity to reflect the current year's rates.

Procedure

  1. In the Contract frame, click the Contract that contains the validity to be copied.
  2. In the Validity frame, in the validities grid, click the validity to be copied.
  3. Click Copy.
    A copy of the validity appears at the bottom of the list in the grid.
  4. Click the new validity.
  5. Click Edit.
  6. Update the validity rules and details as needed.
  7. In the Validity frame, click Save.