About Build Weeks

The Build Weeks step allows you to show and edit selected runs in a worksheet grid.

It allows you to perform the following tasks:
  • Filter the rows that are shown in the grid using the options to the left of the grid.
  • See the details of each run in the grid, including calculated pay time.
  • Sort the grid on any column. This sort is retained if the screen is closed and reopened.
  • Change a run name, shift type, start time, or end time.
  • Change lunch start or lunch end times.
  • Calculate and show pay time for each run.

    Optionally, calculate and show additional columns showing key pre-trip and post-trip clock times covered by driver work rules and included in pay time calculations.

  • Assign a work (bid) number to each run.

    For rostering, this is the bid pick number.

    For cafeteria-style picking, the work number might be used to enter an employee id.

    The lowest unused workid is shown for convenience.

  • Add or delete a run.