Restoring Runs
Runs that have been changed or split can be restored as needed.
- Open the Daily Activity screen and set the Context (F3).
-
Select the piece of work to restore.
If this is a split piece of work, select any one of the pieces.
-
Select Restore Run:
To better see columns in the Restore Run dialog, resize the dialog or the individual columns.
If the run can't be restored because required data isn't found, a message appears and the run is unchanged.